array(8) { ["description"]=> string(648) "1,100-car parking structure adjacent to St. Joseph’s Regional Medical Center. New seven-story, 370,000 sq. ft. precast concrete facility. The project was completed under a design/build contract includes a single story, 20,000 sq. ft. retail building.
Torcon’s contract included demolition of an existing 500-car garage on the site. Midway through construction of the new garage, the existing garage experienced a structural failure and had to be closed. Torcon successfully expedited construction of the new facility, delivering 400 spaces fully seven months ahead of schedule and the entire garage five months ahead of schedule.
" ["details"]=> array(3) { ["location"]=> string(20) "Paterson, New Jersey" ["architect"]=> string(34) "Carl Walker Parking/DMR Architects" ["key_facts"]=> array(3) { [0]=> array(1) { ["text"]=> string(12) "Design Build" } [1]=> array(1) { ["text"]=> string(15) "370,000 sq. ft." } [2]=> array(1) { ["text"]=> string(10) "1100 cars " } } } ["featured_image"]=> int(1046) ["full_width_images"]=> array(1) { [0]=> int(1046) } ["left_column_images"]=> array(2) { [0]=> int(1045) [1]=> int(1043) } ["right_column_images"]=> array(1) { [0]=> int(1042) } ["client"]=> string(38) "St. Joseph’s Regional Medical Center" ["short_description"]=> string(0) "" }
Parking Garage
1,100-car parking structure adjacent to St. Joseph’s Regional Medical Center. New seven-story, 370,000 sq. ft. precast concrete facility. The project was completed under a design/build contract includes a single story, 20,000 sq. ft. retail building.
Torcon’s contract included demolition of an existing 500-car garage on the site. Midway through construction of the new garage, the existing garage experienced a structural failure and had to be closed. Torcon successfully expedited construction of the new facility, delivering 400 spaces fully seven months ahead of schedule and the entire garage five months ahead of schedule.